Past Performance

Design and Reconstruction Jalalabad Air Field Runway for the US Air Force

Reconstruction and Expansion Runway of Jalalabad Air Field, The US Air Force Forward Operating Base Fenty, Afghanistan.

Bamyan Airport Construction for UNOPS

Design and Construction of Passenger Terminal, Firefighting Station, and all phases of runway construction, paving, and marking, as well as design and construction of other passenger amenities, site drainage, underground tunnel and security improvements in Bamyan, Afghanistan.

  • Design and Construction of South of Sharana Road.

  • Item description
  • Item description
  • Item description
  • Item description
  • Item description
  • Item description
  • Item description
  • Item description
  • Item description
  • Item description

Projects Completed

  • Design and Construction of South of Sharana Road, for the US Army in Afghanistan

  • Item description
  • Item description
  • Item description
  • Design and Construction of ANP Maidan shahr, Maidan Wardak Province

    Location

    Maidan Shahr – Maidan Wardak Province

    Client

    United States Army Corps of Engineering (USACE)

    Start and end date of the contract

    09/May/2009 – 13/May/2012

    Total contract amount

    $2,100,212.12

    Contact details including phone and email addresses.

    Email: david.e.carte@usace.army.mil    

    Telephone: +93 (0) 791 512 718

  • Rehabilitation and Construction of 23.5KM DBST Road from Asab Abad to Manugai District, of Kunar Province.

    Location

    Asad Abad to Manugai – Kunar Province

    ·Client

    PRT Kunar

    Start and end date of the contract

    24/December/2009 – 25/November/2010

    Total contract amount

    $7,295,105.00

    ·Contact details including phone and email addresses.

    Email: richar.neckreson@afg.usmc.mil

    Telephone: DSN: 318.349.6317

  • Design and Construction of ANP Markazi Behsood, Maidan Wardak Province

    Location

    Markazi Behsood – Maidan Wardak Province

    · Client

    United States Army Corps of Engineering (USACE)

    Start and end date of the contract

    09/January/2012 – 23/March/2013

    Total contract amount

    $1,869,750.00

    Contact details including phone and email addresses.

    Email: david.e.carte@usace.army.mil    

    Telephone: +93 (0) 791 512 718

  • Designing and Upgrading a Power Plant System

    Location

    Gamberi Base – Laghman Province

    ·Client

    United States Army Corps of Engineering (USACE)

    Start and end date of the contract

    29/November/2012 – 15/May/2013

    Total contract amount

    $203,520.00

    Contact details including phone and email addresses.

    Email: frank.sanchez@usace.army.mil    

    Telephone: +93 (0) 79-680-2258

  • Item description